Construction was completed in November of 1995
for this $2.6M Presumpscot River Bridge near Falmouth, Maine.
Cianbro Corporation, Pittsfield, Maine elected to build this
conventional, 180’ span spandrel arch bridge with an
unconventional method. Instead of using shoring in the river,
(which was limited by the EPA to the period between June 1
and September 30) Cianbro elected to use cable stays to suspend
the arch during erection, resulting in a substantial savings
in schedule and cost.
The stay system consisted of 1” diameter
high strength steel post-tensioning bars. The arch was divided
into 25 ft. long sections with a stub of 13 ft. at the thrust
block. At each 25 ft. segment, 2 bars were anchored to a “through”
tube cast into the arch. The other end of the bars were anchored
in the cap at the main bents. The backstays were anchored
on the opposing face of the bent cap and anchored in the abutment
footing. The thrust of approximately 500 kips was resisted
by the weight of the abutment which was keyed into the rock
ledge. Reinforcing dowels were drilled into the rock to provide
a positive connection to the ledge and to provide an additional
safety against slip and overturning.
Erection began by casting a 13 ft. stub section
of the arch. The forms for this were supported on a temporary
prop. The forms for the next 25 ft. segment were pre-assembled
on the ground and flown into position using a crane parked
on the old bridge (which was left in place for access). Once
the formwork was stripped, the final 25 ft. closure at the
top of the arch was cast re-using the forms, but supporting
them on the free ends of the arch halves. The casting cycle
for each pair of segments was approximately two weeks and
the entire arch erection was completed in less than three
months.
Services
Provided:
• Design and Sequencing of Erection
• Helped Contractor Develop Details Consistent with
Stay Support System
• Provided Shop Drawings, Form Design, Arch Re-design,
Geometry Control, and Camber
• On and Off-Site Technical Assistance