The Page Avenue Extension Project carries Missouri
Route 364 from St. Louis County across the Missouri River
flood plain to St. Charles County, Missouri.
Five traffic lanes, with full shoulders on each side, will
carry traffic eastbound and westbound across the southern
portion of the Creve Coeur Lake Memorial Park in St. Louis
County.
The bridges are cast-in-place in balanced cantilever utilizing
form travelers. Each bridge has a dual-box cross-section measuring
26.05 meters in width. Finley McNary provided the construction
engineering including the construction analysis, geometry
control, segment shop drawings and post-tensioning calculations.
To assist with the schedule and constructibility of the project,
the typical segments were increased to 5.0 meters in length
and the segment layout revised to limit the structure to half
segment out-of-balance during construction. The post-tensioning
layout was revised to accommodate the revised segment layout
and to eliminate the web post-tensioning as originally designed.
Services
Provided:
• Integrated Segment Shop Drawings
• Geometrical Control for Segment Casting
• Casting Curves
• Analysis of Construction Sequence and Loading
• Redesign for Construction Modification
• Erection Procedures
• Post-Tensioning Calculations
• On and Off-Site Technical Assistance