Florida Department of Transportation’s
first major bridge design/build contract, the Blackwater River
Bridge, was an emergency design/build bridge replacement of
twin 3,000-ft. long bridges with one mile of approach roadway
and associated civil work. FINLEY submitted a bid of $30.44M
for the project with a 627 calendar-day construction schedule.
Continuous plate girder construction with typical approach
spans of 184-ft. was utilized for the superstructure. The
channel unit has a three span structure with spans of 184-ft.,
220-ft., and 184-ft. The girder profile was constant with
no haunched webs, and horizontal curvature was accommodated
using heat-curved girders. Twin girder assemblies were constructed
on barges, lifted into place, and field-spliced to adjacent
assembles. Temporary shoring towers and bracing were not required.
The substructure consists of pile foundations, supporting
waterline footings and hammerhead piers which have been cast-in-place
and sized for future widening.
Traylor was able to complete construction of the substructure
for the Westbound Bridge within five months. Extensive use
of Mechanically Stabilized Earth Walls was necessary due to
limited right-of-way. HDPE (high density polyethylene) straps
were utilized in lieu of metal straps due to the corrosive
potential of the tidal surge associated with a hurricane.
The first bridge was completed and opened to traffic in the
Fall of 1996. The two existing bridges were demolished and
the second new bridge was completed in the summer of 1997.
Services
Provided:
• Prepared Technical Proposal for Evaluation by FDOT
• Integrated Segment Drawings
• Geometrical Control of Casting, Erection, and Procedural
Manuals
• Analysis of Construction Loading
• Design of Erection Equipment and Falsework
• Erection Procedures
• Post-Tensioning Calculations
• On and Off-Site Technical Assistance