The largest single construction contract
ever in the Commonwealth of Massachusetts, known as C09A4,
was given notice to proceed in January of 1997, with a bid
price of $397M. This project features several complicated
structures and construction operations including the largest
frozen ground jack tube tunneling operation in the world.
While segmental structures represent only approximately 10%
of the total contract value, they too are very intricate.
A conventional crane and an overhead gantry, manufactured
by DEAL of Udine, Italy, were utilized for the construction
of the viaducts. Pier segments are typically erected by crane
in advance of the gantry. This gantry is extremely versatile,
having a symmetrical design allowing erection in either direction.
Equipped with two segment hoists for simultaneous erection
of two cantilever segments, the gantry is also capable of
supporting the two simple spans during construction. Design
of the viaducts was based primarily on the balanced cantilever
method with the span-by-span method used for two shorter spans.
Span lengths range from 105 ft to 216 ft. Instead of utilizing
the typical expansion joints located at piers to separate
the bridge units, four hinge-spans occur within the viaducts.
These are erected in typical balanced cantilever, temporarily
locked, and then released as erection of subsequent spans
has been completed.
Casting of the 1,062 segments began in September 1998 utilizing
four forms, with completion of the project anticipated in
April of 2001.
Services
Provided:
• Integrated Segment Drawings
• Geometrical Control of Casting, Erection, and Procedural
Manuals
• Casting Curves
• Analysis of Construction Loading
• Design of Erection Equipment and Falsework
• Erection Procedures
• Post-Tensioning Calculations
• On and Off-Site Technical Assistance